Notice: Some procurement information has moved to the Vendor Services section on AustinTexas.gov/FSD as of April 12, 2024, and is no longer be available in this location.

CONTRACT INFORMATION

Contract Number Description
MA - 6100 - SA210000011 HORNSBY BEND BMP PROCESS AMMONIA REMOVAL FACILITY
Contract Details

Percentages

Percent Time
Expended/Remaining:
Percent Amount
Expended/Remaining:

Contract Controls

Begin Date: 02/24/21
Planned Expiration Date: 02/23/25
Authorized Amount: $2,038,767.75
Amount Expended: $866,183.39

Supporting Materials

Order List: View Order List  
Contract: Not Available Online
Authority: Item 004 on 11/12/2020  
Solicitation: Awarded Non-Competitively; No Solicitation, Tabulation or Evaluation Matrix Available.
Goods and Services to be provided
STANTEC CONSULTING SERVICES INC
Commodity Description Commodity
WASTE WATER TREATMENT ENGINEERING
WASTE WATER TREATMENT ENGINEERING-MAJOR SCOPE
92596
Contact
For more information, contact:

Buyer Information

Capital Contracting

Mailing Address

P.O. Box 1088
Austin, TX 78767

Location

Municipal Building
124 W. 8th Street
Room 308
Austin, TX 78701-2302