CT-6100-21080900827 | CISTERN SUBSTATION CUT-IN AND CKT 3121/3136 OPGW ADDITION

CONTRACT INFORMATION

Contract Number Description
CT - 6100 - 21080900827 CISTERN SUBSTATION CUT-IN AND CKT 3121/3136 OPGW ADDITION
Contract Details

Percentages

Percent Time
Expended/Remaining:
Percent Amount
Expended/Remaining:

Contract Controls

Begin Date: 07/07/22
Planned Expiration Date: Open
Authorized Amount: $1,531,693.61
Amount Expended: $786,699.32

Supporting Materials

Order List: Not Applicable
Contract: Not Available Online
Authority: Item 022 on 07/29/2021  
Solicitation: No Solicitation Link
Goods and Services to be provided
Kiewit Infrastructure South Co.
Commodity Description Commodity
MAINTENANCE AND REPAIR, POWER PLANT
MAINTENANCE & REPAIR, POWER PLANT
91256
Contact Office Information
For more information, contact:
Capital Contracting Office

Contact Information

Mailing Address

P.O. Box 1088
Austin, TX 78767

Location

Municipal Building
124 W. 8th Street
Room 308
Austin, TX 78701-2302