Important: Users must meet new password security requirements effective February 12, 2025. Click HERE to review the requirements and change your password.

Data Drill Down for All Months & All Years

ACTIVITY
CATEGORY CONTRACTUALS
EXPENSE CATEGORY SERVICES-CONSTRUCTION CONTR
DEPARTMENT AVIATION
FUND 2018 ABIA CONSTRUCTION REVBONDS
PROGRAM 2016A REVENUE BONDS PARENT
ACTIVITY Select an activity.
PAYEE
PAYMENT REQUEST
Activities | Select from Below
ACTIVITY AMOUNT
ARFF CANOPY $161,982.50
BUILDING DEMOLITION CONSTRUCTION $3,604,126.00
BULK WATER STATION FOR DEICING TRUCKS $41,468.91
CARGO FACILITY EXPANSION $7,713,420.01
CHECKPOINT ONE REMODEL $941,796.66
CONSOLIDATED MAINTENANCE FACILITY - CONSTRUCTION $63,016,509.16
CONSOLIDATED MAINTENANCE FACILITY - DESIGN $21,219.94
ELEVATOR REFURBISHMENTS REBID $939,174.00
EXIST.TERM.CENT.BHS -INTERNATIONAL PROCESS IMPROVEMENT GMP 8 $5,028,208.42
EXISTING TERM CENTRALIZED B.H.S. - W-INFILL SITE WORK GMP 5 $3,508,136.97
EXISTING TERMINAL B.H.S. - WEST INFILL CONSTRUCTION GMP 7 $186,744.44
EXISTING TERMINAL CENTRALIZED B.H.S ENABLING KABA LANES GMP4 $2,264,528.49
EXISTING TERMINAL CENTRALIZED B.H.S. - DESIGN BUILD (GMP1) $6,196,661.43
EXISTING TERMINAL CENTRALIZED B.H.S. - GMP2 LONG LEAD ITEMS $26,870,569.11
EXISTING TERMINAL CENTRALIZED B.H.S. - WESTINFILL DEMO GMP 6 $2,827,969.91
NEW INFORMATION TECHNOLOGY BLDG - REMODEL & ADDITION DESIGN $994,434.00
NEW INFORMATION TECHNOLOGY BUILDING - CONSTRUCTION $33,166,962.88
NEW TERMINAL CENTRALIZED BAGGAGE HANDLING SYSTEM- DESIGN $1,213,775.00
PARKING GARAGE WEST LOT A $46,518,970.00
RENOVATE LEARNING RESOURCE CENTER FOR AVIATION OFFICE SPACE $8,641,481.01
T-HANGER ROOF REPLACEMENT $53,876.04
TERMINAL - APRON EXPANSION AND IMPROVEMENTS PROJECT $19,617,183.00
TERMINAL HYDRONIC HOT WATER PIPE IMPROVEMENTS $218,849.96
TERMINAL HYDRONIC HOT WATER PIPE IMPROVEMENTS PHASE 1 $666,414.04
TERMINAL HYDRONIC HOT WATER PIPE IMPROVEMENTS PHASE 2 $1,093,716.00
TRACON BUILDING STORMWATER IMPROVEMENTS $1,936,485.22
-