Data Drill Down for All Months & All Years

PAYMENT REQUEST
CATEGORY CONTRACTUALS
EXPENSE CATEGORY SERVICES-CONSTRUCTION CONTR
DEPARTMENT AUSTIN WATER
FUND WASTEWATER IMPROVEMENTS--NVA
PROGRAM WASTEWATER FUTURE PROJECTS UNF
ACTIVITY ACWP-GOVALLE 4-4TH ST WW IMPS
PAYEE OSCAR RENDA CONTRACTING INC
PAYMENT REQUEST Select a payment request.
Payment Requests | Select from Below
PAYMENT REQUEST DESCRIPTION CHECK DATE CHECK STATUS  AMOUNT
PRM 6100 11100600633 Construction, Pipeline 10/07/2011 Paid $85,624.52
PRM 6100 11050922215 Construction, Pipeline 05/10/2011 Paid $138,681.89
PRM 6100 11012111276 Construction, Sewer and Storm Drain 01/24/2011 Paid $271,922.43
PRM 6100 10102703317 Construction, Pipeline 10/28/2010 Paid $129,231.30
PRM 6100 10081333767 Construction, Pipeline 08/16/2010 Paid $177,990.66
PRM 6100 10060225871 Construction, Pipeline 06/03/2010 Paid $154,970.30
PRM 6100 10040620239 Construction, Pipeline 04/07/2010 Paid $78,965.76
PRM 6100 10031117367 Construction, Pipeline 03/12/2010 Paid $236,373.48
PRM 6100 10020112719 Construction, Pipeline 02/02/2010 Paid $193,496.71
PRM 6100 09120707207 Construction, Pipeline 12/08/2009 Paid $1,059,434.65
PRM 6100 09110203593 Construction, Pipeline 11/03/2009 Paid $240,975.23
PRM 6100 09102002216 Construction, Pipeline 10/21/2009 Paid $204,499.44
PRM 6100 09100500345 Construction, Pipeline 10/06/2009 Paid $824,190.71
PRM 6100 09100500345 Construction, Sewer and Storm Drain 10/06/2009 Paid $161,403.35
PRM 6100 09090943203 Construction, Pipeline 09/10/2009 Paid $137,939.80
PRM 6100 09090843061 Construction, Pipeline 09/09/2009 Paid $465,228.11
PRM 6100 09081340176 Construction, Pipeline 08/14/2009 Paid $27,127.25
PRM 6100 09080338912 Construction, Pipeline 08/04/2009 Paid $241,497.94
PRM 6100 09080338912 Construction, Sewer and Storm Drain 08/04/2009 Paid $40,560.25
PRM 6100 09070635315 Construction, Pipeline 07/07/2009 Paid $254,037.36
PRM 6100 09070635315 Construction, Sewer and Storm Drain 07/07/2009 Paid $28,075.35
PRM 6100 09060131447 Construction, Pipeline 06/02/2009 Paid $80,595.15
PRM 6100 09050428274 Construction, Pipeline 05/05/2009 Paid $548,488.20
PRM 6100 09040624634 Construction, Pipeline 04/07/2009 Paid $379,900.40
PRM 6100 09040624634 Construction, Sewer and Storm Drain 04/07/2009 Paid $399,150.36
PRM 6100 09040324409 Construction, Pipeline 04/06/2009 Paid $933,097.68
PRM 6100 09030319932 Construction, Pipeline 03/04/2009 Paid $1,630,501.88
PRM 6100 09030219733 Construction, Pipeline 03/03/2009 Paid $157,872.22
PRM 6100 09021317972 Construction, Pipeline 02/17/2009 Paid $107,350.00
PRM 6100 09020216114 Construction, Pipeline 02/03/2009 Paid $580,818.60
PRM 6100 09013015947 Construction, Pipeline 02/02/2009 Paid $1,477,817.03
PRM 6100 09010512147 Construction, Pipeline 01/06/2009 Paid $71,768.70
PRM 6100 08123011667 Construction, Pipeline 12/31/2008 Paid $443,502.75
PRM 6100 08121009999 Construction, Pipeline 12/11/2008 Paid $228,294.19
PRM 6100 08120208644 Construction, Pipeline 12/03/2008 Paid $458,457.48
PRM 6100 08120208645 Construction, Pipeline 12/03/2008 Paid $200,450.00
PRM 6100 08110404961 Construction, Pipeline 11/05/2008 Paid $1,377,062.74
PRM 6100 08110404962 Construction, Pipeline 11/05/2008 Paid $73,150.00
PRM 6100 08110404963 Construction, Pipeline 11/05/2008 Paid $898,659.23
PRM 6100 08100600795 Construction, Pipeline 10/07/2008 Paid $1,521,283.16