Notice: As of April 12, 2024, we moved some information on this site. Visit AustinTexas.gov/FSD to find Financial Documents, Performance Management, Unclaimed Property, and Contact information.

Data Drill Down for All Months & All Years

PAYMENT REQUEST
CATEGORY CONTRACTUALS
EXPENSE CATEGORY SERVICES-CONSTRUCTION CONTR
DEPARTMENT AUSTIN WATER
FUND S-WASTEWATER IMPROVEMENTS
PROGRAM HORNSBY BEND THICKENER COMPLEX REHAB CONSTRUCTION
ACTIVITY MISCELLANEOUS
PAYEE MATOUS CONSTRUCTION LTD
PAYMENT REQUEST Select a payment request.
Payment Requests | Select from Below
PAYMENT REQUEST DESCRIPTION CHECK DATE CHECK STATUS  AMOUNT
PRM 6100 22080227831 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/04/2022 Paid $120,000.00
PRM 6100 21092032677 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 09/22/2021 Paid $128,826.00
PRM 6100 21081929672 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/23/2021 Paid $87,446.20
PRM 6100 21071626463 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 07/20/2021 Paid $79,514.97
PRM 6100 21062123532 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/23/2021 Paid $137,115.00
PRM 6100 21051820592 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 05/20/2021 Paid $888,811.83
PRM 6100 21041917642 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 04/21/2021 Paid $34,480.49
PRM 6100 21031714701 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 03/19/2021 Paid $190,827.28
PRM 6100 21022212211 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 02/24/2021 Paid $76,324.80
PRM 6100 21011909438 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 01/21/2021 Paid $192,920.89
PRM 6100 21010107984 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 01/05/2021 Paid $127,573.82
PRM 6100 20111604081 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 11/18/2020 Paid $58,725.49
PRM 6100 20101901834 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 10/21/2020 Paid $116,902.92
PRM 6100 20092535043 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 09/29/2020 Paid $173,829.86
PRM 6100 20082531986 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/27/2020 Paid $533,363.85
PRM 6100 20072028426 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 07/22/2020 Paid $630,185.09
PRM 6100 20061525469 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/19/2020 Paid $844,842.25
PRM 6100 20051923336 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 05/22/2020 Paid $302,409.70
PRM 6100 20042120625 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 04/24/2020 Paid $1,845,184.40
PRM 6100 20031817208 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 03/20/2020 Paid $990,645.48
PRM 6100 20021813929 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 02/20/2020 Paid $700,461.61
PRM 6100 20012110435 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 01/23/2020 Paid $288,615.01
PRM 6100 19121707306 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 12/19/2019 Paid $478,222.86
PRM 6100 19111804834 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 11/21/2019 Paid $606,423.22
PRM 6100 19102102105 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 10/24/2019 Paid $424,430.28
PRM 6100 19091732937 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 09/19/2019 Paid $227,509.83
PRM 6100 19081930225 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/21/2019 Paid $1,218,388.64
PRM 6100 19071626791 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 07/19/2019 Paid $850,743.05
PRM 6100 19061924370 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/21/2019 Paid $1,105,729.70
PRM 6100 19060522973 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/07/2019 Paid $466,283.75
PRM 6100 19041517914 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 04/17/2019 Paid $739,569.30
PRM 6100 19032715993 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 03/29/2019 Paid $491,446.40
PRM 6100 19021912335 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 02/21/2019 Paid $826,248.25
PRM 6100 19012209174 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 01/24/2019 Paid $175,750.00