Notice: As of April 12, 2024, we moved some information on this site. Visit AustinTexas.gov/FSD to find Financial Documents, Performance Management, Unclaimed Property, and Contact information.

Data Drill Down for All Months & All Years

PAYMENT REQUEST
DEPARTMENT PUBLIC WORKS - TRANSPORTATION
FUND TRANSPORTATION FUND
PROGRAM STREET PREVENTIVE MAINTENANCE
ACTIVITY ASPHALT OVERLAY
EXPENSE CATEGORY ASPHALT
PAYEE IRONHORSE ASPHALT LTD
PAYMENT REQUEST Select a payment request.
PAYMENT REQUESTS | Select from Below
PAYMENT REQUEST DESCRIPTION CHECK DATE CHECK STATUS 
Checks cleared as of 01/31/2015 have been reflected as paid on the reports
AMOUNT
PRM 6200 10012712189 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 01/28/2010 Paid $19,581.69
PRM 6200 10010610016 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 01/07/2010 Paid $21,827.05
PRM 6200 09123009238 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 12/31/2009 Paid $701.50
PRM 6200 09122308639 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 12/28/2009 Paid $39,893.71
PRM 6200 09121007505 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 12/11/2009 Paid $5,826.27
PRM 6200 09120206747 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 12/03/2009 Paid $58,464.57
PRM 6200 09120206748 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 12/03/2009 Paid $27,901.84
PRM 6200 09112305929 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 11/24/2009 Paid $9,866.16
PRM 6200 09111605216 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 11/17/2009 Paid $2,036.53
PRM 6200 09110203598 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 11/03/2009 Paid $36,957.74
PRM 6200 09102803108 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 10/29/2009 Paid $3,124.68
PRM 6200 09101401647 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 10/15/2009 Paid $117,689.22
PRM 6200 09100700679 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 10/08/2009 Paid $119,102.34
PRM 6200 09092545185 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 09/28/2009 Paid $21,562.76
PRM 6200 09092444980 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 09/25/2009 Paid $127,592.27
PRM 6200 09090943227 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 09/10/2009 Paid $48,885.98
PRM 6200 09090943228 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 09/10/2009 Paid $103,587.24
PRM 6200 09090442879 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 09/08/2009 Paid $143,499.58
PRM 6200 09090342706 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 09/04/2009 Paid $44,254.44
PRM 6200 09082842053 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 08/31/2009 Paid $3,860.44
PRM 6200 09082441376 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 08/25/2009 Paid $48,001.23
PRM 6200 09082041024 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 08/21/2009 Paid $47,596.10
PRM 6200 09081840696 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 08/19/2009 Paid $15,980.65
PRM 6200 09081740537 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 08/18/2009 Paid $46,023.42
PRM 6200 09080639357 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 08/07/2009 Paid $58,609.67
PRM 6200 09073138742 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 08/03/2009 Paid $86,052.00
PRM 6200 09072938401 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 07/30/2009 Paid $6,790.97
PRM 6200 09072838149 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 07/29/2009 Paid $19,974.32
PRM 6200 09072237291 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 07/23/2009 Paid $79,167.49
PRM 6200 09070935720 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 07/10/2009 Paid $92,284.49
PRM 6200 09062534509 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 06/26/2009 Paid $74,395.64
PRM 6200 09062233959 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 06/23/2009 Paid $14,463.45
PRM 6200 09061633254 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 06/17/2009 Paid $29,940.00
PRM 6200 09060932516 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 06/10/2009 Paid $48,447.69
PRM 6200 09060832298 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 06/09/2009 Paid $220.24
PRM 6200 09052630768 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 05/27/2009 Paid $52,074.84
PRM 6200 09052130292 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 05/22/2009 Paid $19,537.10
PRM 6200 09051929924 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 05/20/2009 Paid $92,398.15
PRM 6200 09051429593 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 05/15/2009 Paid $66,797.13
PRM 6200 09050528477 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 05/06/2009 Paid $45,965.25
PRM 6200 09042427215 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 04/27/2009 Paid $3,484.27
PRM 6200 09042126764 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 04/22/2009 Paid $32,865.65
PRM 6200 09041726329 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 04/20/2009 Paid $100,274.00
PRM 6200 09040825068 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 04/09/2009 Paid $46,873.93
PRM 6200 09040123876 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 04/02/2009 Paid $57,451.93
PRM 6200 09033123696 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 04/01/2009 Paid $31,652.42
PRM 6200 09032723393 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 03/30/2009 Paid $65,140.71
PRM 6200 09032322544 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 03/24/2009 Paid $73,178.61
PRM 6200 09031121198 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 03/12/2009 Paid $13,415.54
PRM 6200 09030920798 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 03/10/2009 Paid $69,448.16
PRM 6200 09030420192 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 03/05/2009 Paid $39,157.95
PRM 6200 09022318969 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 02/24/2009 Paid $10,939.62
PRM 6200 09022018842 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 02/23/2009 Paid $67,991.31
PRM 6200 09021918569 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 02/20/2009 Paid $651.47
PRM 6200 09021017424 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 02/11/2009 Paid $50,203.07
PRM 6200 09012815597 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 01/29/2009 Paid $2,947.94
PRM 6200 09012314890 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 01/26/2009 Paid $27,739.24
PRM 6200 09012214682 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 01/23/2009 Paid $168.03
PRM 6200 09010712675 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 01/08/2009 Paid $673.76
PRM 6200 08123111907 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 01/02/2009 Paid $995.70
PRM 6200 08122911489 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 12/30/2008 Paid $18,179.23
PRM 6200 08120308912 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 12/04/2008 Paid $52,926.42
PRM 6200 08112007255 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 11/21/2008 Paid $167,082.90
PRM 6200 08110605389 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 11/07/2008 Paid $39,417.89
PRM 6200 08110605390 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 11/07/2008 Paid $61,306.88
PRM 6200 08103104651 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 11/03/2008 Paid $133,293.53
PRM 6200 08102002847 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 10/21/2008 Paid $545.43
PRM 6200 08101702762 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 10/20/2008 Paid $4,659.82
PRM 6200 08101602526 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 10/17/2008 Paid $6,347.78
PRM 6200 08101502296 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 10/16/2008 Paid $68,673.80
PRM 6200 08101001475 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 10/13/2008 Paid $15,275.89
PRM 6200 08100901276 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 10/10/2008 Paid $32,371.33
PRM 6200 08100700907 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 10/08/2008 Paid $27,958.38
PRM 6200 08093056140 ASPHALTIC CONCRETE, HOT MIX, IN ACCORDANCE WITH IT 10/01/2008 Paid $41,015.03
The data contained on this website is for informational purposes only and contains expenditure information for the City of Austin. Certain Austin Energy transactions have been excluded as competitive matters under Texas Government Code Section 552.133 and City Council Resolution 20051201-002; therefore, the line amounts may not reflect the total check amount if certain Austin Energy invoices were included on the check.