PAYMENT REQUEST
DEPARTMENT AUSTIN WATER
FUND W-WATER IMPROVEMENTS
PROGRAM FORT UPPER BASIN WATER PIPELINE RENEWAL
ACTIVITY MISCELLANEOUS
EXPENSE CATEGORY SERVICES-CONSTRUCTION CONTR
PAYEE FACILITIES REHABILITATION INC
PAYMENT REQUEST Select a payment request.
PAYMENT REQUESTS | Select from Below
PAYMENT REQUEST DESCRIPTION CHECK DATE CHECK STATUS 
Checks cleared as of 01/31/2015 have been reflected as paid on the reports
AMOUNT
PRM 6100 24022115839 Construction, Sewer and Storm Drain 02/23/2024 Paid $1,241.95
PRM 6100 23080430412 Construction, Sewer and Storm Drain 08/08/2023 Paid $36,432.58
PRM 6100 23071728378 Construction, Sewer and Storm Drain 07/19/2023 Paid $19,346.56
PRM 6100 23060624218 Construction, Sewer and Storm Drain 06/08/2023 Paid $47,513.72
PRM 6100 23050220827 Construction, Sewer and Storm Drain 05/04/2023 Paid $111,161.86
PRM 6100 23030614794 Construction, Sewer and Storm Drain 03/08/2023 Paid $458.33
PRM 6100 22121407332 Construction, Sewer and Storm Drain 12/16/2022 Paid $4,640.32
PRM 6100 22102703112 Construction, Sewer and Storm Drain 10/31/2022 Paid $548.08
The data contained on this website is for informational purposes only and contains expenditure information for the City of Austin. Certain Austin Energy transactions have been excluded as competitive matters under Texas Government Code Section 552.133 and City Council Resolution 20051201-002; therefore, the line amounts may not reflect the total check amount if certain Austin Energy invoices were included on the check.