PRM 6100 24041522437 Site Work 04/16/2024 Outstanding $1,934,542.06
PRM 6100 24022316266 Site Work 02/27/2024 Paid $1,760,041.21
PRM 6100 23121308178 Site Work 12/18/2023 Paid $1,277,360.58
PRM 6100 23103003394 Site Work 11/02/2023 Paid $333,007.06
PRM 6100 23091835379 Site Work 09/19/2023 Paid $2,018,719.12
PRM 6100 23032917350 Site Work 03/30/2023 Paid $1,916,196.55
PRM 6100 15061828369 General Construction: Management, Scheduling, Cost 06/22/2015 Paid $469,627.46
PRM 6100 15061828370 General Construction: Management, Scheduling, Cost 06/22/2015 Paid $52,014.00
PRM 6100 15060426839 General Construction: Management, Scheduling, Cost 06/10/2015 Paid $30,580.00
PRM 6100 15060426840 General Construction: Management, Scheduling, Cost 06/10/2015 Paid $377,656.90
PRM 6100 15051324729 General Construction: Management, Scheduling, Cost 05/18/2015 Paid $95,839.80
PRM 6100 15051324733 General Construction: Management, Scheduling, Cost 05/18/2015 Paid $13,679.62
PRM 6100 15051324734 General Construction: Management, Scheduling, Cost 05/18/2015 Paid $46,465.03
PRM 6100 15051324735 General Construction: Management, Scheduling, Cost 05/18/2015 Paid $40,277.69
PRM 6100 15051324736 General Construction: Management, Scheduling, Cost 05/18/2015 Paid $14,554.00
PRM 6100 15040320051 General Construction: Management, Scheduling, Cost 04/06/2015 Paid $30,933.43
PRM 6100 15033019438 General Construction: Management, Scheduling, Cost 04/02/2015 Paid $47,562.74
PRM 6100 15033019439 General Construction: Management, Scheduling, Cost 04/02/2015 Paid $70,013.05
PRM 6100 15033019440 General Construction: Management, Scheduling, Cost 04/02/2015 Paid $950.00
PRM 6100 15033019441 General Construction: Management, Scheduling, Cost 04/02/2015 Paid $3,625.95
PRM 6100 15033019442 General Construction: Management, Scheduling, Cost 04/02/2015 Paid $146.07
PRM 6100 15033019443 General Construction: Management, Scheduling, Cost 04/02/2015 Paid $703.57
PRM 6100 15033019444 General Construction: Management, Scheduling, Cost 04/02/2015 Paid $34,422.14
PRM 6100 15033019445 General Construction: Management, Scheduling, Cost 04/02/2015 Paid $16,601.50
PRM 6100 15033019446 General Construction: Management, Scheduling, Cost 04/02/2015 Paid $58,777.81
PRM 6100 15033019447 General Construction: Management, Scheduling, Cost 04/02/2015 Paid $24,381.06
PRM 6100 15033019448 General Construction: Management, Scheduling, Cost 04/02/2015 Paid $12,450.39
PRM 6100 15033119657 General Construction: Management, Scheduling, Cost 04/02/2015 Paid $24,225.00
PRM 6100 15022515577 General Construction: Management, Scheduling, Cost 02/27/2015 Paid $576,219.90
PRM 6100 15022615768 General Construction: Management, Scheduling, Cost 02/27/2015 Paid $609,194.25
PRM 6100 15021914819 General Construction: Management, Scheduling, Cost 02/20/2015 Paid $814,585.85
PRM 6100 15021013820 General Construction: Management, Scheduling, Cost 02/12/2015 Paid $136,954.06
PRM 6100 15021013822 General Construction: Management, Scheduling, Cost 02/12/2015 Paid $243,283.93
PRM 6100 15021114050 General Construction: Management, Scheduling, Cost 02/12/2015 Paid $66,027.60
PRM 6100 15021114063 General Construction: Management, Scheduling, Cost 02/12/2015 Paid $41,767.00
PRM 6100 15012612045 General Construction: Management, Scheduling, Cost 01/28/2015 Paid $246,564.45
PRM 6100 15012612047 General Construction: Management, Scheduling, Cost 01/28/2015 Paid $1,676.28
PRM 6100 15012311918 General Construction: Management, Scheduling, Cost 01/26/2015 Paid $149,009.47
PRM 6100 15012311919 General Construction: Management, Scheduling, Cost 01/26/2015 Paid $7,124.98
PRM 6100 15012311920 General Construction: Management, Scheduling, Cost 01/26/2015 Paid $990,165.58
PRM 6100 15012311921 General Construction: Management, Scheduling, Cost 01/26/2015 Paid $755,497.45
PRM 6100 15012311922 General Construction: Management, Scheduling, Cost 01/26/2015 Paid $121,925.54
PRM 6100 15012311923 General Construction: Management, Scheduling, Cost 01/26/2015 Paid $13,405.40
PRM 6100 15012311924 General Construction: Management, Scheduling, Cost 01/26/2015 Paid $189,019.98
PRM 6100 15012311925 General Construction: Management, Scheduling, Cost 01/26/2015 Paid $150,998.52
PRM 6100 15012311926 General Construction: Management, Scheduling, Cost 01/26/2015 Paid $17,660.50
PRM 6100 15012311927 General Construction: Management, Scheduling, Cost 01/26/2015 Paid $288,343.56
PRM 6100 15012311928 General Construction: Management, Scheduling, Cost 01/26/2015 Paid $525,314.38
PRM 6100 15012311929 General Construction: Management, Scheduling, Cost 01/26/2015 Paid $181,792.15
PRM 6100 14123009294 General Construction: Management, Scheduling, Cost 12/31/2014 Paid $975,433.91
PRM 6100 14123009298 General Construction: Management, Scheduling, Cost 12/31/2014 Paid $37,050.00
PRM 6100 14120206339 General Construction: Management, Scheduling, Cost 12/03/2014 Paid $1,739,574.79
PRM 6100 14102302948 General Construction: Management, Scheduling, Cost 10/27/2014 Paid $305,147.41
PRM 6100 14102403017 General Construction: Management, Scheduling, Cost 10/27/2014 Paid $831,145.95
PRM 6100 14102403019 General Construction: Management, Scheduling, Cost 10/27/2014 Paid $1,409,130.87
PRM 6100 14100100068 General Construction: Management, Scheduling, Cost 10/02/2014 Paid $173,978.38
PRM 6100 14092638294 General Construction: Management, Scheduling, Cost 09/30/2014 Paid $270,855.14
PRM 6100 14092638296 General Construction: Management, Scheduling, Cost 09/30/2014 Paid $2,203,345.96
PRM 6100 14092638298 General Construction: Management, Scheduling, Cost 09/30/2014 Paid $377,031.25
PRM 6100 14082534555 Civil Engineering 08/26/2014 Paid $553,526.23
PRM 6100 14082534557 Civil Engineering 08/26/2014 Paid $1,161,437.72
PRM 6100 14082134311 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/25/2014 Paid $213,464.24
PRM 6100 14082134311 Civil Engineering 08/25/2014 Paid $961,400.29
PRM 6100 14073132069 Civil Engineering 08/01/2014 Paid $96,730.01
PRM 6100 14072831437 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 07/29/2014 Paid $327,619.59
PRM 6100 14072831437 Civil Engineering 07/29/2014 Paid $2,213,429.25
PRM 6100 14062327159 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/24/2014 Paid $151,573.00
PRM 6100 14062327159 Civil Engineering 06/24/2014 Paid $2,524,426.72
PRM 6100 14062327161 Civil Engineering 06/24/2014 Paid $631,750.00
PRM 6100 14060224964 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/04/2014 Paid $48,942.00
PRM 6100 14060224964 Civil Engineering 06/04/2014 Paid $865,624.32
PRM 6100 14060224966 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/04/2014 Paid $727,846.15
PRM 6100 14060224966 Civil Engineering 06/04/2014 Paid $1,328,052.11
PRM 6100 14053024857 Civil Engineering 06/03/2014 Paid $2,346,671.86
PRM 6100 14060224965 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/03/2014 Paid $29,321.30
PRM 6100 14042521167 Civil Engineering 04/29/2014 Paid $34,124.55
PRM 6100 14042421051 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 04/25/2014 Paid $47,451.27
PRM 6100 14042421051 Civil Engineering 04/25/2014 Paid $315,310.27
PRM 6100 14041820505 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 04/21/2014 Paid $276,520.63
PRM 6100 14041820505 Civil Engineering 04/21/2014 Paid $7,210,546.24
PRM 6100 14032817946 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 03/31/2014 Paid $185,536.76
PRM 6100 14032417478 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 03/26/2014 Paid $3,121,632.43
PRM 6100 14031416525 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 03/18/2014 Paid $63,998.05
PRM 6100 14031416525 Civil Engineering 03/18/2014 Paid $6,598,845.39
PRM 6100 14031416530 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 03/18/2014 Paid $6,143.72
PRM 6100 14021313437 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 02/18/2014 Paid $1,158,801.46
PRM 6100 14021313437 Civil Engineering 02/18/2014 Paid $6,757,833.99
PRM 6100 14011511052 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 01/16/2014 Paid $24,006.04
PRM 6100 14010709855 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 01/09/2014 Paid $197,947.51
PRM 6100 14010709855 Civil Engineering 01/09/2014 Paid $1,028,399.42
PRM 6100 14010709857 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 01/09/2014 Paid $73,099.95
PRM 6100 14010709857 Civil Engineering 01/09/2014 Paid $58,653.31
PRM 6100 14010709859 Civil Engineering 01/09/2014 Paid $947,486.88
PRM 6100 14010709861 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 01/09/2014 Paid $7,035.71
PRM 6100 14010709861 Civil Engineering 01/09/2014 Paid $240,737.24
PRM 6100 14010709863 Civil Engineering 01/09/2014 Paid $3,142,696.09
PRM 6100 13112706372 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 12/02/2013 Paid $1,058,948.58
PRM 6100 13112706372 Civil Engineering 12/02/2013 Paid $6,406,126.64
PRM 6100 13111204975 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 11/13/2013 Paid $276,521.35
PRM 6100 13111204975 Civil Engineering 11/13/2013 Paid $1,358,032.85
PRM 6100 13111204977 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 11/13/2013 Paid $129,347.25
PRM 6100 13111204979 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 11/13/2013 Paid $258,836.86
PRM 6100 13111204981 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 11/13/2013 Paid $8,814.42
PRM 6100 13111204981 Civil Engineering 11/13/2013 Paid $5,891,665.56
PRM 6100 13111204983 Civil Engineering 11/13/2013 Paid $1,991,949.35
PRM 6100 13100900933 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 10/10/2013 Paid $2,669.59
PRM 6100 13100900933 Civil Engineering 10/10/2013 Paid $1,277,333.97
PRM 6100 13100900935 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 10/10/2013 Paid $989,030.19
PRM 6100 13100900935 Civil Engineering 10/10/2013 Paid $3,768,371.06
PRM 6100 13090934253 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 09/10/2013 Paid $642,755.08
PRM 6100 13090934253 Civil Engineering 09/10/2013 Paid $4,988,639.43
PRM 6100 13080631505 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/14/2013 Paid $237.50
PRM 6100 13080631504 Civil Engineering 08/08/2013 Paid $1,356,632.54
PRM 6100 13080631506 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/08/2013 Paid $3,716.40
PRM 6100 13080631508 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/08/2013 Paid $168,917.60
PRM 6100 13080631510 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/08/2013 Paid $1,426,172.36
PRM 6100 13080631512 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/08/2013 Paid $145,472.31
PRM 6100 13080631512 Civil Engineering 08/08/2013 Paid $3,776,968.27
PRM 6100 13080631514 Civil Engineering 08/08/2013 Paid $231,189.49
PRM 6100 13071127948 Civil Engineering 07/12/2013 Paid $177,648.08
PRM 6100 13070127068 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 07/05/2013 Paid $1,281,824.66
PRM 6100 13070127068 Civil Engineering 07/05/2013 Paid $18,500.00
PRM 6100 13070227136 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 07/05/2013 Paid $394,854.61
PRM 6100 13070227138 Civil Engineering 07/05/2013 Paid $789,724.01
PRM 6100 13070227141 Civil Engineering 07/05/2013 Paid $3,107,379.65
PRM 6100 13070227144 Civil Engineering 07/05/2013 Paid $2,102,434.44
PRM 6100 13060524987 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/07/2013 Paid $22,281.59
PRM 6100 13060524987 Civil Engineering 06/07/2013 Paid $1,149,766.99
PRM 6100 13060524989 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/07/2013 Paid $1,324,626.11
PRM 6100 13060625124 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/07/2013 Paid $333,100.89
PRM 6100 13060625124 Civil Engineering 06/07/2013 Paid $3,686,704.32
PRM 6100 13051322630 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 05/15/2013 Paid $3,233,598.72
PRM 6100 13051322630 Civil Engineering 05/15/2013 Paid $7,048,412.95
PRM 6100 13040919226 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 04/10/2013 Paid $1,572,805.72
PRM 6100 13040919226 Civil Engineering 04/10/2013 Paid $7,275,564.28
PRM 6100 13030816373 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 03/12/2013 Paid $1,011,803.88
PRM 6100 13030816373 Civil Engineering 03/12/2013 Paid $259,558.95
PRM 6100 13030816375 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 03/12/2013 Paid $369,463.17
PRM 6100 13030816378 Civil Engineering 03/12/2013 Paid $617,604.80
PRM 6100 13030816381 Civil Engineering 03/12/2013 Paid $369,542.04
PRM 6100 13030816384 Civil Engineering 03/12/2013 Paid $2,394,642.57
PRM 6100 13030816386 Civil Engineering 03/12/2013 Paid $252,564.96
PRM 6100 13030816391 Civil Engineering 03/12/2013 Paid $593,232.25
PRM 6100 13030816398 Civil Engineering 03/12/2013 Paid $1,273,524.72
PRM 6100 13013012677 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 02/05/2013 Paid $1,400,541.01
PRM 6100 13013012677 Civil Engineering 02/05/2013 Paid $2,400,128.10
PRM 6100 13013112792 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 02/05/2013 Paid $645,854.65
PRM 6100 13013112792 Civil Engineering 02/05/2013 Paid $4,562,494.15
PRM 6100 12122708626 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 01/02/2013 Paid $927,309.70
PRM 6100 12122708626 Civil Engineering 01/02/2013 Paid $6,260,371.42
PRM 6100 12122708631 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 01/02/2013 Paid $1,324,300.17
PRM 6100 12122708631 Civil Engineering 01/02/2013 Paid $2,848,965.59
PRM 6100 12122708638 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 01/02/2013 Paid $112,476.01
PRM 6100 12113006352 Civil Engineering 12/05/2012 Paid $7,347,492.23
PRM 6100 12120306413 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 12/05/2012 Paid $2,669,729.82
PRM 6100 12120306413 Civil Engineering 12/05/2012 Paid $1,351,653.84
PRM 6100 12110804615 Civil Engineering 11/09/2012 Paid $300,000.00
PRM 6100 12110704486 Civil Engineering 11/08/2012 Paid $18,616.24
PRM 6100 12110203906 Civil Engineering 11/06/2012 Paid $129,983.75
PRM 6100 12110203913 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 11/06/2012 Paid $1,109,397.56
PRM 6100 12110203913 Civil Engineering 11/06/2012 Paid $4,715,027.58
PRM 6100 12110203915 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 11/06/2012 Paid $2,351,609.85
PRM 6100 12110203915 Civil Engineering 11/06/2012 Paid $1,304,516.39
PRM 6100 12100100049 Civil Engineering 10/05/2012 Paid $255,406.16
PRM 6100 12100100048 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 10/03/2012 Paid $2,426,190.27
PRM 6100 12100100050 Civil Engineering 10/03/2012 Paid $734,938.26
PRM 6100 12100100056 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 10/03/2012 Paid $242,157.03
PRM 6100 12100100056 Civil Engineering 10/03/2012 Paid $3,478,650.13
PRM 6100 12082932240 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/30/2012 Paid $2,816,546.70
PRM 6100 12082932240 Civil Engineering 08/30/2012 Paid $4,062,760.13
PRM 6100 12082932242 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/30/2012 Paid $4,504.19
PRC 6100 12051100155 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/10/2012 Paid $3,603,606.46
PRC 6100 12051100156 Civil Engineering 08/10/2012 Paid $372,390.51
PRC 6100 12051100157 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/10/2012 Paid $165,386.42
PRC 6100 12051100158 Civil Engineering 08/10/2012 Paid $823,330.80
PRC 6100 12051100159 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/10/2012 Paid $154,269.41
PRC 6100 12051100160 Civil Engineering 08/10/2012 Paid $275,072.90
PRC 6100 12051100162 Civil Engineering 08/10/2012 Paid $139,510.35
PRC 6100 12051100163 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/10/2012 Paid $48,329.48
PRC 6100 12051100164 Civil Engineering 08/10/2012 Paid $111,741.61
PRC 6100 12051100165 Civil Engineering 08/10/2012 Paid $464,200.07
PRC 6100 12051100166 Civil Engineering 08/10/2012 Paid $2,198,020.64
PRC 6100 12051100167 Civil Engineering 08/10/2012 Paid $265,289.33
PRC 6100 12051100171 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/10/2012 Paid $218,556.73
PRC 6100 12051100172 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/10/2012 Paid $859,459.37
PRC 6100 12051100173 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/10/2012 Paid $203,481.34
PRM 6100 12080930054 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/10/2012 Paid $136,714.37
PRM 6100 12080930070 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/10/2012 Paid $460,042.42
PRM 6100 12080729706 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/08/2012 Paid $5,277,810.11
PRM 6100 12080729706 Civil Engineering 08/08/2012 Paid $4,583,830.09
PRM 6100 12080629540 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/07/2012 Paid $460,042.42
PRM 6100 12080629542 Civil Engineering 08/07/2012 Paid $832,153.91
PRM 6100 12062725751 Civil Engineering 06/28/2012 Paid $860,959.65
PRM 6100 12062725753 Civil Engineering 06/28/2012 Paid $288,071.36
PRM 6100 12062725755 Civil Engineering 06/28/2012 Paid $400,000.00
PRM 6100 12062725757 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/28/2012 Paid $17,037.78
PRM 6100 12062725759 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/28/2012 Paid $2,228,775.23
PRM 6100 12062725761 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/28/2012 Paid $1,151,099.49
PRM 6100 12062725763 Civil Engineering 06/28/2012 Paid $3,096,224.90
PRM 6100 12061224079 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/13/2012 Paid $122,392.97
PRM 6100 12060723735 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/08/2012 Paid $7,815,650.61
PRM 6100 12060723735 Civil Engineering 06/08/2012 Paid $4,054,411.46
PRM 6100 12041919108 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 04/23/2012 Paid $159,362.20
PRM 6100 12041919108 Civil Engineering 04/23/2012 Paid $1,331,925.00
PRM 6100 12041218321 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 04/16/2012 Paid $4,614,758.99
PRM 6100 12041218321 Civil Engineering 04/16/2012 Paid $1,727,106.47
PRM 6100 12031215229 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 03/14/2012 Paid $4,099,550.00
PRM 6100 12031215229 Civil Engineering 03/14/2012 Paid $4,007,103.84
PRM 6100 12020711765 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 02/09/2012 Paid $3,558,492.67
PRM 6100 12011309719 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 01/18/2012 Paid $3,701,782.20
PRM 6100 11120906746 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 12/13/2011 Paid $4,648,806.48
PRM 6100 11110804071 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 11/09/2011 Paid $6,882,901.50
PRM 6100 11093036074 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 10/03/2011 Paid $4,254,020.59
PRM 6100 11090633607 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 09/08/2011 Paid $2,487,481.23
PRM 6100 11081731718 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 08/18/2011 Paid $3,590,350.12
PRM 6100 11072829604 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 07/29/2011 Paid $376,779.98
PRM 6100 11071528374 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 07/18/2011 Paid $2,534,400.78
PRM 6100 11061325323 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/15/2011 Paid $804,113.54
PRM 6100 11061425511 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 06/15/2011 Paid $932,802.04
PRM 6100 11051122520 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 05/13/2011 Paid $3,230,960.63
PRM 6100 11042020414 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 04/22/2011 Paid $2,823,485.27
PRM 6100 11031817001 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 03/21/2011 Paid $1,994,367.54
PRM 6100 11021013247 CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT 02/14/2011 Paid $900,380.08